Portal de Yecla

www.portaldeyecla.com

Yecla - SpanishYecla - English
detail of Yecla

 

27 companies choose to work indoor pool (27/10/2016)

The works completed in the last quarter of 2017

On Wednesday the jury for the award of the renovation of the Municipal Pool Deck met.

Some works whose budget amounts to 1,828,343.52 euros and will involve the construction of more than 2,300 m2.

27 companies are vying for the award of this important for upgrading sports facilities in Yecla work, a work in which a new vessel designed for teaching, changing rooms and ancillary spaces such as reception, offices, toy library will be built , self-service bar or gallery for spectators.

After this first meeting of the jury, municipal technical services will require the necessary documentation to companies opting to grant to continue with the tender process next week and be able to award these works in the coming weeks.

Almost all the works of this phase of the reform of the Municipal Pool Deck are projected to be completed during the last quarter of 2017 and that the work can be performed while maintaining the pool service to all users.

Source: Ayuntamiento de Yecla

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información