The action is part of the improvement of 1.5 kilometers from the center that the City is taking place in recent months
Have started, as planned, the refurbishment of the streets and Child Hospital in the section between Pizarro and the Arch of the Child.
The works were postponed to not hamper business and festive celebrations center during the past December.
The arrangement of these two roads continued, from the street and even Master Polo Pizarro, is part of the redevelopment of the center of town that the council is carrying out in recent months.
In this campaign will also include work on the street don Lucio, the environment of the Plaza of Spain, and street improvements Miguel Golf and Placeta Murillo and Ortega.
Taken together, these actions involve the remodeling of the depth of 1.5 miles of public roads through a municipal investment of nearly 2 million.
The arrangement of streets and Child Hospital in the investment of nearly half a million euros, includes the entire road paved with granite high strength to withstand traffic, and installation of new sewerage systems, drinking water and telecommunications.
The new streetlights will be subject to the facades of buildings, so the streets will gain space.
They installed some trees with its walkable tree pits, so as not to disturb the crosswalk, and a dozen banks and some boxes of garbage collection in underground containers.
Also create areas for loading and unloading of goods to service businesses.
During construction, which will be undertaken in three phases, has also been provided to enable loading and unloading areas for the interim zone activity is not affected.
Source: Ayuntamiento de Yecla