Work begins on road Fuentealamo (26/09/2011)

The expected execution time is 12 months |

Have started remodeling work on the road to fulfilling the commitment Fuentealamo by the Minister of Public Works, Antonio Sevilla in the last meeting held in late August in Murcia with the Mayor and Councillor for Works and Urban Development.

Despite the difficulties, the Regional Government thus maintained its commitment to undertake these works that are so necessary to facilitate a more comfortable communication, seamless access to many rural areas and urban case of Yecla.

The works consist in fitting the first 6.5 kilometers of road linking RM-404 Yecla in Fuente Alamo and have a regional investment exceeding 1.6 billion euros.

The planned implementation period is 12 months.

It will widen the existing roadway width of five meters to nine meters, with one lane in each direction of 3.5 meters and one meter shoulders.

Also be appropriate to give the track curves with a minimum radius of 130 meters and will replace the firm with hot asphalt around the object of stage acting.

Also, be provided access to adjoining properties through service roads along the path with a width of six meters.

Also, nine are projected surface drainage for proper water drainage and renewal of all signage, marking and installation of safety barriers in the points.

In addition, it will proceed with the construction of two new roundabouts, a 42-meter outer radius at the beginning of the road at its intersection with the RM-A18, which also connects the town with the neighboring province and its population of Montealegre's Castillo, and another at mile 1, outer radius 34 meters, providing access to the tennis club and where is recorded daily over more than 2,500 vehicles.

This new infrastructure, which will have two lanes from four meters each, and will have access for installing the lighting system, with a total of 29 low-power lamps.

Also placed reflector edge and milestones to enhance nighttime visibility.

In the first kilometer of the road in the area near the town center, there will be a bike lane ten feet wide adjacent to the right side of the road and separated by a curb of the roadway.

Source: Ayuntamiento de Yecla

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información