After the first phase of road works Fuentealamo (11/07/2013)

The Mayor of Yecla, Mark Ortuño reiterated "the need to complete the refurbishment of this important activity in improving communication between many rural and town of Yecla".

The Director of Public Works, Antonio Sevilla, accompanied by the Mayor of Yecla, Mark Ortuño, visited the refurbishment Fuentealamo the road, in its first phase, completed recently.

The intervention involved the refurbishment of the first 6.4 kilometers of road linking RM-404 Yecla with Fuente Alamo, with a regional investment of 1.6 million euros.

The Mayor of Yecla, Ortuño Marcos has reiterated, in the course of the visit, "the need to complete the refurbishment of this road to the end of the municipality, as it is a significant improvement of communications between many rural areas and helmet Yecla city ".

The works in this first phase, have widened the roadway width 5 meters to 9.5 meters, with a lane in each direction of 3.5 meters and a meter shoulders.

It is also suitable for plotting curves provide a minimum radius of 130 meters and is back strong with hot asphalt over the entire length of the performance object.

Also, there have been nine surface drainage for proper water drainage and renewal of all signage, marking and installation of safety barriers in the points.

We proceeded to the construction of two new roundabouts, a 42 meter outer radius at the beginning of the road at its intersection with the RM-A18, which also connects the city with the neighboring province and its population of Montealegre del Castillo, and another at mile 1 of 34 meters outer radius, providing access to the tennis club and which records the daily passage of more than 2,500 vehicles.

These new infrastructures have two lanes four meters each, and access feature installation for lighting system, with a total of 29 lamps of low consumption.

Furthermore, landmarks are placed to reinforce reflector edge and nighttime visibility.

In the first mile of the road, in the area close to the town center, there is a bike path three feet wide adjacent to the right side of the road and separated by a curb of the roadway.

Source: Ayuntamiento de Yecla

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información