It enables students to access Azorín Institute works on the stretch of the old crossing (17/09/2009)

Councillor for Infrastructure, Works and Urbanism, Ortuño Marcos met with the Director of the Institute Azorín, Casimiro Chirlaque, and José Antonio Teruel, Director of Public Works Trimtor company, awarded the new phase of redevelopment of the former Traverse Yecla to try to solve the problems that the works may cause to students of the Centre, at the start of the new school.

"The special feature has motivated the development project cutting the road from San Roque to Camino Real, both road and pedestrian traffic during the works last month, but now that classes have resumed, it should access is enabled delimited and clearly marked with appropriate security measures to ensure the passage of students in this section of works, "said Councilman Mark Ortuño.

The second phase of the redevelopment of the former Traverse Yecla is close to completion because the work is developing normally and meeting deadlines.

It is expected that the new road is put into operation in late October.

Useful information

Project: Preparation of N-344 Voyage a.

Phase II.

C / Camino Real, C / San Roque to C / Valencia.

Project Objective: To provide continuity and uniformity to the axis that form the Old Crossing Street Yecla and Camino Real.

Make this street in a safer, more functional and aesthetic, improving the urban area and adapting to the environment with a base type that stretches from East to West.

Awarded Company: Company TRIMTOR, SA

Duration of Works: Five months (Commencement of Works: May 25, 2009).

Project Features:

Change asphalt paving.

Lighting change.

Construction of sidewalks.

Construction of gardens, with trees and irrigation system.

Renovation of the sewage drains.

Renovation of drinking water network.

Relocation of traffic light signal.

Install traffic signal vertical and horizontal.

Installation of street furniture, bollards and railings.

Pre-installation of telecommunications infrastructure.

Budget Allocation: '38 € 334,261 (+ VAT)

Finance: Local Investment Fund for Employment - Government of Spain.

Source: Ayuntamiento de Yecla

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información